We attended a large extension project in West Yorkshire to lift six steel beams into place with our spider crane.
Starting at the front of the property we set up the crane on the driveway to lift the first support beams into place. With rain forecast we also set up our gazebo until the weather passed. When the front beams were fixed in place we moved the crane to the rear, where we set up the crane again inside the extension. Here there was space to expand the outriggers fully. This allowed the heavy six meter steels to be lifted safely into place. The steel clamp was used here to adjust the steels for a perfect fit.